Engineering commissioning of HL-2M vacuum system

CAO Cheng-zhi, CAO Zeng, RAN Hong, XIE Yan-feng, CAI Xiao, JI Xiao-quan, ZHONG Wu-lü, YANG Qing-wei, MAO Wei-cheng, HL-2M Development Team#br#   

  1. (Southwestern Institute of Physics, Chengdu 610041) 
  • Received:2021-04-27 Revised:2021-07-17 Online:2021-10-15 Published:2021-11-19

HL-2M 装置真空系统调试运行

曹诚志,曹 曾,冉 红,颉延风,蔡 潇,季小全, 钟武律,杨青巍,毛维成,HL-2M 研制团队
  

  1. (核工业西南物理研究院,成都 610041) 
  • 作者简介:曹诚志(1985−),男,四川乐山人,博士,副研究员,主要从事聚变真空科学与技术、等离子体与壁相互作 用研究。
  • 基金资助:
    国家重点研发计划(2017YFE0301305,2017YFE0301300) 

Abstract: In the phase of initial completion of the device, the clarification on the items of engineering 
commissioning of vacuum and the development of reasonable commissioning scheme are conducive to the 
functional confirmation, troubleshooting, and the efficient coordinated operation of various systems. And it can 
prepare discharge conditions for the initial plasma discharge of HL-2M tokamak. The vacuum system of device 
consists of the ultra-high vacuum pumping system, the wall conditions and the gas injection system. Based on the 
defined objective, the interface sheets are sorted out, and the commissioning schemes and schedules are 
formulated for each subsystem and integrated system. The preparation of the vacuum environment, first wall and 
fueling of the device has been completed, and it provides essential conditions for the first plasma of HL-2M 
tokamak. 

Key words: HL-2M tokamak, Vacuum system, Engineering commissioning 

摘要: 在装置初步建成阶段,有序地开展真空系统的调试内容梳理,制定合理的调试步骤和调试方案,有
利于装置各系统的功能确认和故障排除,高效地开展各系统协同运行,为 HL-2M 装置初始等离子体放电提供装
置辅助系统层面的放电条件准备。装置真空系统主要涉及超高真空抽气系统、器壁处理系统和送气加料系统等。
基于制定的联调目标,针对 HL-2M 装置真空相关系统开展了界面关系梳理、子系统调试方案制定、系统工程联
调步骤和方案的拟定等工作,通过联调完成了装置在真空获得、壁处理、加料等方面的条件准备,为初始放电提
供了基本保障。 

关键词: HL-2M 装置;真空系统;系统调试 